Renderings of the Main Venue of 2021 Asian Youth Games were Stunningly Unveiled
Date: 2019-11-15      Source: Shantou Daily


The highly concerned venue project of the 2021 Asian Youth Games has set off a construction upsurge in an all-round way: the pile foundation construction of the stadium and gymnasium is in full swing, with a total number of 2,768 pipe piles, which is expected to be completed by November 22. At the same time, the foundation slab excavation will be alternately carried out with pipe pile works with the flow operation method. According to the schedule, the construction for the foundation slabs of the first floor will be completed before December 31, and the construction of the main works of the venue will start next year.
  
The main venue of the Asian Youth Games consists of a 22,000-seat stadium, an 8,000-seat gymnasium (including training hall), a conference center, a training ground, an outdoor large-scale platform and the outdoor auxiliary works. The overall construction will display the characteristics of Shantou's marine culture. The  implied meaning "Flying Waves" will create a landmark building serving the Asian Youth Games and daily recreational-sports activities on the east coast of Shantou. The project was officially started on July 31 this year and is scheduled to be completed by May 31, 2021, with a total construction period of 22 months.

Source:Shantou Daily,Nov 15, 2019


2021年亚青会主场馆效果图惊艳亮相  

备受关注的2021年亚青会体育场馆项目全面掀起施工建设热潮:体育场、体育馆桩基础施工全面铺开,管桩总数2768根,预计1122日前全部完成;同时,基础底板开挖随管桩穿插流水作业,按计划1231日前完成首层基础底板的施工,明年开始全面转入场馆主体工程的建设。  

亚青会主场馆主要包括一座2.2万座位体育场,一座8000座位体育馆(含训练馆)、会议中心、训练场和室外大平台以及室外附属配套工程等,整体建设将展现汕头海洋文化特色,设计寓意飞舞的浪花,在汕头东海岸打造一个服务亚青会和日常文体活动的地标性建筑。项目于今年731日正式开工,计划于2021531日前竣工,总工期22个月。

来源:汕头日报2019-11-15



 