Since work resumption after Spring Festival, Jinwan Park and East Coast Park projects, covering an area of 609 mu, have been propelling the construction at full speed by three shifts in a day of 24 hours. According to the schedule, the parks will be completed and open to public on October 1 with the earthworks and pipe pile construction completed in April, and all parks completed by the end of September.
The Jinwan Park and East Coast Park are located in Group E and Group F of the Xinjin area of the East Coast New Town, composed of three relatively independent parks and green spaces, with a total investment of about 340 million yuan. The park's green space is divided into four parks as per the distribution of land, and takes time sequence as main line: the first park "Ring of Time", the second park "Time Valley", the third park "Dream Takeoff" and the fourth park "Embracing the Future". As the first park launched to be constructed on the East Coast New Town, the project will be conducive to the improvement of municipal facilities in Xinjin District and serve as an international Shantou "Urban Living Room" with Chaoshan style when it is completed.
Source:Shantou Daily, March 27, 2020
汕头津湾、东海岸公园“十一”将建成开园
占地609亩的津湾、东海岸公园项目,自春节后复工以来,采取三班倒24小时不间断施工的方式全速推进建设,4月将完成全部土方及管桩施工,9月底完成所有园建施工,计划“十一”建成开园。
津湾、东海岸公园位于东海岸新城新津片区E、F组团,由3个相对独立的公园绿地组成,总投资额约3.4亿元。公园绿地依据地块分布,分为四个园区,并以时间脉络为主线:第一园区为“时间之环”,第二园区为“时间溪谷”,第三园区为“梦想腾飞”,第四园区为“拥抱未来”。作为东海岸新城首座启动建设的公园,项目建成后将有利于完善新津片区市政配套,打造成国际范兼具潮汕特色的汕头“城市客厅”。
来源:汕头日报2020-3-27