At midday of May 27, Unit 1 of Cogeneration Project in the Chaonan Printing and Dyeing Center successfully combined to the grid for power generation, with all economic and technical indicators reaching excellent levels, which will better serve the printing and dyeing enterprises entering the park.
The Chaonan Printing and Dyeing Center Cogeneration Project (Shantou Zhongsheng Keying Thermal Power Generation Co., Ltd.) serves as the "Energy Island" of the park, covering an area of about 140 mu (23.06 acres).The project mainly builds a 970 tons/hour high-temperature ultra-high pressure circulating fluidized bed boiler and a 100,000-kilowatt back-pressure generator set. The overall plan and main project of the generator sets and boilers are "5 boilers and 4 generator sets" and supporting desulfurization and denitration equipment, with the total steam supply capacity of 970 tons/hour, and the total generated power of 100,000 kilowatts.
Source:Shantou Daily, May 31, 2020
汕头潮南印染中心热电联产项目1号机组并网发电
5月27日中午,潮南印染中心热电联产项目1号机组并网发电成功,各项经济技术指标均达到优良水平,将更好地服务入园印染企业生产。
潮南印染中心热电联产项目(汕头中圣科营热电有限公司)是园区的“能源岛”,占地面积约140亩。该项目主要建设970吨/小时高温超高压循环流化床锅炉和10万千瓦背压式发电机组,机炉配置总体方案和主体工程为“5炉4机”及配套的脱硫脱硝设备,总供汽能力为970吨/小时,总发电功率达10万千瓦。
来源:汕头日报2020-5-31