On December 7, all the 35 wind turbines of Datang Nan’ao Lemen I Offshore Wind Power Project — the first offshore wind power project in Shantou City, were all hoisted, laying a solid foundation for starting the homestretch for achieving the goal of full-capacity grid-connected power generation at the end of the year.
As one of the important deployments of Datang Group's new energy development strategy in the South China Sea, the Nan’ao Project is currently simultaneously advancing key tasks such as submarine cable laying and grid-connection debugging. After the Project is completed, it is expected to generate 751 million kilowatt-hours of electricity per year, with an output value of RMB 565 million. Compared with conventional coal-fired thermal power units with the same power generation capacity, it can save about 240,000 tons of standard coal and reduce 450,000 tons of carbon dioxide emissions per year. It is of great significance for Shantou to accelerate the establishment of a new industrial development landscape of "three new, two specials, one big" ("three new" means new energy, new materials and new generation of electronic information industries; "two features" means two traditional industries with distinctive local features, namely, textile and clothing and creative toys; "one big" means big health industry), promote the upgrading of energy structure, and take solid steps toward the national goals of “achieving peak carbon emissions and carbon neutrality”.
Source:Shantou Daily, Dec 8, 2021
大唐南澳勒门I 海上风电项目冲刺年底全容量并网发电
12月7日,汕头市首个海上风电项目——大唐南澳勒门I海上风电项目35台风机全部吊装完成,为年底冲刺全容量并网目标打下了坚实的基础。
南澳项目作为大唐集团在南海海域新能源发展战略的重要部署之一,目前正同步推进海缆敷设、并网调试等关键工作。该项目建成后,预计年发电量7.51亿度,产值5.65亿元;与相同发电量的常规燃煤火电机组相比,每年可节约标煤约24万吨,减少二氧化碳排放45万吨,对助力汕头加快构建“三新两特一大”产业发展新格局,促进能源结构升级,践行国家“碳达峰、碳中和”目标具有重要意义。
来源:汕头日报 2021-12-8