The prefabricated small box girders for the approach span of the Jingzao Bridge Project (the Phase III Project of Chaozhou-Shantou Loop Expressway), which was constructed by China Railway Major Bridge Engineering Group Co., Ltd., were all erected on May 27. So far, the approach span had been connected, and the Project had fully entered the stage of bridge deck system and ancillary construction.
The Jingzao Bridge Project of Chaozhou-Shantou Loop Expressway connects with the Liaison Line of Chaozhou-Shantou Loop Expressway. It crosses the Rongjiang South River from south to north, and connects with Shantou City and Jieyang City, with a total project length of 3,110 meters. What had been completed this time was the approach span of the main bridge on the north bank side of Jingzao Bridge, with a total of 430 small box girders erected. Up to now, 90% of the overall works of the Jingzao Bridge Project of Chaozhou-Shantou Loop Expressway has been completed. Currently, the construction of both the bridge deck system and the ancillary project is being simultaneously advanced in an orderly manner, and every effort is being made to complete the construction of Jingzao Bridge and open it to traffic at the end of this year.
Source:Shantou Daily, May 29, 2024
潮汕环线高速京灶大桥引桥拉通
5月27日,由中铁大桥局承建的潮汕环线高速三期工程京灶大桥项目引桥预制小箱梁全部架设完成,至此引桥段实现拉通,全面进入桥面系及附属施工阶段。
潮汕环线高速京灶大桥项目连接潮汕环线高速潮汕联络线,自南向北跨越榕江南河,连接汕头、揭阳两地,项目总长3110米。此次完成架设为京灶大桥主桥北岸侧引桥,共架设小箱梁430片。目前,潮汕环线高速京灶大桥项目总体工程已完成90%,同时,大桥桥面系及附属工程正同步有序推进,全力攻坚大桥年底建成通车目标。
来源:汕头日报 2024-5-27