The first girder of the whole line of Eastern Guangdong East Intercity Railway was successfully erected on May 30, marking that the Project had entered the box girder erection stage from the box girder prefabrication stage.
Jinping Girder Fabrication Yard, which completed the erection of the first box girder this time, covers an area of about 170 mu (about 11.33 hectares), with a maximum storage capacity of 160 girders. It is the largest box girder erection base for the whole line of Eastern Guangdong East Intercity Railway, and is responsible for the prefabrication and erection of 1,010 girders. During the erection of the first box girder, the construction team adopted the cross-line girder lifting machine to lift the girder onto the bridge, and then with the collaborative operation of girder-transporting vehicles and bridge-erecting cranes, the first box girder, which was 32.6 meters long and 11.2 meters wide and weighed 600 tons, was finally successfully erected at the designated location.
Source:Shantou Daily, May 31, 2024
粤东城际铁路全线首榀箱梁成功铺架
5月30日,粤东城际铁路全线首榀箱梁成功铺架,标志着该项目从箱梁预制阶段迈入架梁阶段。
此次完成首榀箱梁架设的金平制梁场占地约170亩,最大存梁能力160孔,是粤东城际铁路全线最大的箱梁支架基地,承担1010榀箱梁预制架设任务。首梁架设过程中,建设团队采取跨线提梁机提梁上桥,再借助运梁车、架桥机协同作业,最终成功将长32.6米、宽11.2米,重达600吨的首榀箱梁架设在指定位置。
来源:汕头日报 2024-5-31